Question: WBS Element Planned Value ( PV ) Earned Value ( EV ) Actual Cost ( AC ) 2 . 0 1 Airframe 4 8 ,
WBS Element
Planned Value
PV
Earned Value
EV
Actual Cost
AC
Airframe
Engines
Avionics
Communications
Tech. Manuals
Spares
Training
Project Total
Drug Surveillance Aircraft ProjectMonthly Performance Report
October XX
Consider the project performance report presented in the Figure above. Your analyst has determined that your estimate to complete ETC is $ Based on your performance to date and assuming future performance will proceed at the same level of efficiency as past performance, what is your estimate at completion EAC
WBS Element
Planned Value
PV
Earned Value
EV
Actual Cost
AC
Airframe
Engines
Avionics
Communications
Tech. Manuals
Spares
Training
Project Total
Drug Surveillance Aircraft ProjectMonthly Performance Report
October XX
Consider the project performance report presented in the Figure above. Your analyst has determined that your estimate to complete ETC is $ Based on your performance to date and assuming future performance will proceed at the same level of efficiency as past performance, what is your estimate at completion EAC
$
$
Cannot be determined from the information provided
$
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
