Question: Consider the project whose data are given below. Activity Precedence Relationship Duration (Days) Required Tool Required Crew A 3 2 0 B 3 1 2

Consider the project whose data are given below.

Consider the project whose data are given below. Activity Precedence Relationship Duration (Days) Required Tool Required Crew A 3 2 0 B 3 1 2 A 6 5 0 D A,B 3 3 1 E 5 0 1 F 7 0 5 G D.E 4 6 5 H F G 3 3 0 1 H 5 0 2 What is the earliest completion time of this project if you have only 6 tools and 8 crew member in your project team? Answer: days