Question: Consider the project within the table below. table [ [ Activity , Duration ( days ) , Immediate Predecessors ] , [ A ,
Consider the project within the table below.
tableActivityDuration daysImmediate PredecessorsANoneBNoneCADB CFD E
a Draw the project network using AON notation
b Calculate the early start ES early finish EF late finish LF and late start LS times of each activity. Compute the slack time at each activity.
c What is the critical path? What is the duration of the project?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
