Question: Consider the project within the table below. table [ [ Activity , Duration ( days ) , Immediate Predecessors ] , [ A ,

Consider the project within the table below.
\table[[Activity,Duration (days),Immediate Predecessors],[A,4,None],[B,3,None],[C,6,A],[D,7,B, C],[F,1,D, E]]
a. Draw the project network (using AON notation)
b. Calculate the early start (ES), early finish (EF), late finish (LF) and late start (LS) times of each activity. Compute the slack time at each activity.
c. What is the critical path? What is the duration of the project?
 Consider the project within the table below. \table[[Activity,Duration (days),Immediate Predecessors],[A,4,None],[B,3,None],[C,6,A],[D,7,B, C],[F,1,D,