Question: Consider the simple 3 - station assembly line illustrated below, where the 2 machines at Station 1 are parallel, i . e . , the

Consider the simple 3-station assembly line illustrated below, where the 2 machines at Station 1 are parallel, i.e., the product only needs to go through one of the 2 machines before proceeding to Station 2.
What is the bottleneck time of this process?
A.12min.
B.20min.
C.38min.
D.6min.
E.10min.
10. In the above question, what is the throughput time of this process?
A.12min.
B.20min.
C.38min.
D.18min.
E.58min.
11. Suppose that the demand in period 1 was 7 units and the demand in period 2 was 9 units. Assume that the forecast for period 1 was for 5 units. If the firm uses exponential smoothing with an alpha value of 20, what should be the forecast for period 3?(Round answers to two decimals.)
A.9.00
B.3.72
C.9.48
D.5.00
E.6.12
12. Service level is:
A. the probability of stocking out.
B. the probability of not stocking out.
C. something that should be minimized in retail.
 Consider the simple 3-station assembly line illustrated below, where the 2

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!