Question: Consider the small MRP tree given in Figure 5 . 1 4 A . The master schedule for A - 1 1 0 is as

Consider the small MRP tree given in Figure 5.14A. The master schedule for A-110 is as follows:
\table[[Time Period,1,2,3,4,5,6,7,8,9,10,11,12,13,14,15],[Gross Req'ts,3,6,5,4,3,6,5,2,6,0,6,3,2,5,4]]
Determine the lot-for-lot planned order releases for A-110, A-200, and x-300 in the 15-period planining horizon assuming no scheduled order receibts for any item