Question: Consider the tasks listed below. a) Use the largest candidate rule to balance a line for these tasks. Tc=30 sec. b) What is the efficiency

Consider the tasks listed below. a) Use the

Consider the tasks listed below. a) Use the largest candidate rule to balance a line for these tasks. Tc=30 sec. b) What is the efficiency of the line? (Use your max station time in the calculation)