Question: Consider the two product structure trees shown below, note that both products have D as a component. Suppose we want to develop a material requirement

Consider the two product structure trees shown below, note that both products have D as a
component. Suppose we want to develop a material requirement plan (MRP) for D given this
information: there is a beginning inventory of 110 units of D on hand, and all items have lead
times of one week. The master schedule calls for 80 units of A in week 4 and 50 units of C in
week 5.