Question: Consider the value stream map attached What is the process time for the Handles step? Please show work a. 20 seconds b. 11.8 seconds c.

Consider the value stream map attached

What is the process time for the Handles step?

Please show work

a. 20 seconds

b. 11.8 seconds

c. 5.88 seconds

Consider the value stream map attached What is

daily Customer 30.000 brushes per week 6.000 brushes per day Order Size = 1000 brushes Takt Time - 9.0 seconds Printing Department FG Bristles People- FTE- PT = 875 CT-5.85 SU-0 min B-600 5 batches 3000 brushes Handles People = FTE = PT- CT-5.88 SU = 0 min B = 100 days TOTALS Total Lead Time 05 days 20 secs Total Processing Time seconds

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!