Question: Consider the Work Breakdown Structure of this project ... Activity Immediate Predecessor(s) Duration (days) A none 12 B A 9 C A 8 D B

Consider the Work Breakdown Structure of this project ...

Activity Immediate Predecessor(s) Duration (days)
A none 12
B A 9
C A 8
D B 6
E C, D 9
F C, D 10
G E, F 11

At a minimum, how long will this project take (in days)?