Question: Consider the Work Breakdown Structure of this project ... Activity Immediate Predecessor(s) Duration (days) A none 12 B A 9 C A 8 D B
Consider the Work Breakdown Structure of this project ...
| Activity | Immediate Predecessor(s) | Duration (days) |
| A | none | 12 |
| B | A | 9 |
| C | A | 8 |
| D | B | 6 |
| E | C, D | 9 |
| F | C, D | 10 |
| G | E, F | 11 |
At a minimum, how long will this project take (in days)?