Question: Question 5 3 pts Consider the Work Breakdown Structure of this project... Activity Immediate Predecessor(s) Duration (days) A none 9 B A 10 C A

Question 5 3 pts Consider the Work Breakdown
Question 5 3 pts Consider the Work Breakdown Structure of this project... Activity Immediate Predecessor(s) Duration (days) A none 9 B A 10 C A 7 D B 10 E CD 13 F C D 10 G E, F 6 At a minimum, how long will this project take (in days)