Question: Consider this scenario: A project in its 26th week has an actual cost of $270,000. It was scheduled to have spent $261,000. For the work
Consider this scenario: A project in its 26th week has an actual cost of $270,000. It was scheduled to have spent $261,000. For the work performed to date, the budgeted value is $272,000.
- What are the cost and schedule variances for the project?
- What are the SPI and CPI?