Question: Consider this work breakdown structure to answer the following questions. Activity Immediate precedes Time estimates (day) Optimistic Most likely pessimistic A Start 38 50 62

Consider this work breakdown structure to answer the following questions.

Activity

Immediate precedes

Time estimates (day)

Optimistic

Most likely

pessimistic

A

Start

38

50

62

B

Start

90

99

108

C

Start

85

100

115

D

A

19

25

31

E

B

91

100

115

F

END

D

62

65

68

- What is the estimated expected (mean) time for project completion?

- What is the estimated slack time for activity A?

- What is the probability that this project will be completed within 205 days?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!