Question: Consider the following work breakdown structure: D 62 Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A,B,C A 38 50 B 108 End

Consider the following work breakdown structure:

Consider the following work breakdown structure: D 62 Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A,B,C A 38 50 B 108 End 85 100 115 19 25 31 End 91 100 115 F End 65 68 E 90 99 O A 4 14 62 What is the estimated standard deviation in the time for activity E? Multiple Choice 4 days 24 days O 2 days O 16 days O 3 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!