Question: Consider two mutually exclusive projects, Project 1 and 2. [20 points) 6 7 18 Time 0 1 2 Project 1 -1000 120 120 Project 2

Consider two mutually exclusive projects, Project 1 and 2. [20 points) 6 7 18 Time 0 1 2 Project 1 -1000 120 120 Project 2 -1000 600 600 3 4 300 300 15000 300 0 300 -300 300 -600 300 -1200 The opportunity cost of capital is 12%. (a) Calculate the NPV, IRR, simple and discounted Payback periods for project 1. [7 points) (b) Plot the NPV as a function of the discount rate for both projects. Explain which project should be chosen as a function of the discount rate. [5 points) (c) When capital is almost free, the second project seems unprofitable. Is it a calculation mistake? Provide the intuition for this result. [8 points)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
