Question: Considering a worker's performance it was observed, during a 9 hour shift he was producing 2 5 units. Due to the audit the employee was

Considering a worker's performance it was observed, during a 9 hour shift he was producing 25 units. Due to the audit the employee was extra careful and was working 10% slower than his usual speed. He had 3 allowances with an average of 15%. Calculate the normal time for this employee to produce units?
20 minutes
*19.44 minutes
*18.38 minutes
*26.4 minutes