Question: Considering preemptive priority scheduling answer the following questions: P no. Priority 1 2 3 4 10 20 30 40 AT 0 1 2 4 BT
Considering preemptive priority scheduling answer the following questions: P no. Priority 1 2 3 4 10 20 30 40 AT 0 1 2 4 BT 5 4 2 1 CT TAT WT Calculate the completion time (CT), turnaround time (TAT), waiting time (WT), and average wait time. Please show your work in details