Question: Construct a Gantt Chart assuming each activity starts at the earliest time possible. Based on the following information, how long will the project take to
Construct a Gantt Chart assuming each activity starts at the earliest time possible.
Based on the following information, how long will the project take to complete?
File: GANTT-A.pdf
| Activity | A | B | C | D | E | F | G | H | I | J | K | L | M |
| Predecessor | - | - | A | B | A,B | E | F | F | F | G,H | H,I | J | L |
| Duration(weeks) | 3 | 5 | 5 | 2 | 4 | 5 | 2 | 3 | 4 | 3 | 6 | 1 | 2 |
| 21 weeks | ||
| 22 weeks | ||
| 23 weeks | ||
| 24 weeks | ||
| 25 weeks |