Question: Construct a Gantt Chart assuming each activity starts at the earliest time possible. Based on the following information, how long will the project take to
Construct a Gantt Chart assuming each activity starts at the earliest time possible. Based on the following information, how long will the project take to complete? A B Activity Predecessor Duration(weeks) . 5 - D E F G H 1 AC B CD DE FG GH 3 2 4 4 Am 100/- J B 3 1 3 L M JK KL 2 3 2 5 3 5 2. 28 weeks 29 weeks 30 weeks 31 weeks 32 weeks