Question: Construct a Gantt Chart assuming each activity starts at the earliest time possible. Based on the following information, how long will the project take to

 Construct a Gantt Chart assuming each activity starts at the earliest

Construct a Gantt Chart assuming each activity starts at the earliest time possible. Based on the following information, how long will the project take to complete? A B DEF GH B A.B CD F.G 2 4 5 2 3 - 1 F 4 - Activity Predecessor Duration(weeks) 22 weeks - J H 3 K L HIJ.K 6 1 M L 2 3 5 5 23 weeks 24 weeks 25 weeks 26 weeks