Question: Construct a network diagram using CPM method (AON). Find expected project duration, all possible path with path length, Slack time. Please do not use internet
Construct a network diagram using CPM method (AON). Find expected project duration, all possible path with path length, Slack time. Please do not use internet calculator.
| Activity | Predecessor(s) | Fixed Duration (days) |
| A |
| 4 |
| B |
| 5 |
| C |
| 4 |
| D | B | 9 |
| E | D | 8 |
| F | D | 9 |
| G | A | 2 |
| H | E, G | 6 |
| I | H | 8 |
| J | C | 4 |
| K | J | 7 |
| L | I, K | 3 |
| M | F, L | 5 |