Question: Construct a network diagram using CPM method (AON). Find expected project duration, all possible path with path length, Slack time. Please do not use online
Construct a network diagram using CPM method (AON). Find expected project duration, all possible path with path length, Slack time. Please do not use online calculators they are mostly incorrect.
| Activity | Predecessor(s) | Fixed Duration (days) |
| A |
| 5 |
| B | A | 9 |
| C | A | 4 |
| D | B | 2 |
| E | D | 3 |
| F | E, H | 2 |
| G | B | 11 |
| H | G | 2 |
| I | G | 3 |
| J | C | 2 |
| K | J | 4 |
| L | G,K | 7 |
| M | F,I,L | 2 |