Question: Question 1 Construct a project network for the following project. The project is completed when activities F and G are both complete Activity Immediate Predecessor

Question 1 Construct a project network for the following project. The project is completed when activities F and G are both complete Activity Immediate Predecessor A B D E F G A A CB CB D, E Question 2 Given the information of a project in the table below, Activity Dependency A Time (days) 3 B 2 A 5 D B 5 E CD 6 F CD 2 G F 2 () 0 Produce project network diagram. Find the activity schedule for the project Find the critical path of the project (iv) Find out project time