Question: Construct a Project Network Perform Forward and Backward Pass Determine Project Completion Time Calculate Slack Values State the Critical Path Write down the five answers

Construct a Project Network
Perform Forward and Backward Pass
Determine Project Completion Time
Calculate Slack Values
State the Critical Path
Write down the five answers in the blank space and submit Excel.
\table[[ACTIVT,DescripnoN,TIME (WEEKS),IMMEDLATE PREDE],[A,Build internal components,2,-],[B,Modify roof and floor,3,-],[C,Construct collection stack,2,A],[D,Pour concrete and install frame,4,A, B],[E,Build high-temperatture burner,4,C],[F,Install pollution control system,3,C],[G,Install air pollution device,5,D,E],[H,Inspect and test,2,F,G]]
 Construct a Project Network Perform Forward and Backward Pass Determine Project

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!