Question: a) Table Q3a. shows the logic for a particular project. - C (i) Construct a network diagram showing the various logical activity relationships from this

a) Table Q3a. shows the logic for a particular

a) Table Q3a. shows the logic for a particular project. - C (i) Construct a network diagram showing the various logical activity relationships from this information (ii) Perform a forward and backward pass to complete the activity boxes (iii) Highlight the critical path on your diagram and state the earliest project completion time. Activity Precedence Time (days) A 5 B A 3 A 4 D 4 E 2 F 4 G C 3 . D 5 I D 6 J E, F 3 K G 4 L G 7 M HI 5 N J, K, L 8 O M, N 2 B B B