Question: Construct an Activity on Arrow network diagram, for the project. Analyze the network to determine the earliest and latest event times and the minimum project

Construct an “Activity on Arrow” network diagram, for the project.

Activity Predecessors Duration Workers needed (Days) ($50/Hour) A B C D E

 

Analyze the network to determine the earliest and latest event times and the minimum project duration. Indicate the critical path for the project.

What is the total estimated cost of workers and machines for the project?

Activity Predecessors Duration Workers needed (Days) ($50/Hour) A B C D E F G H I J K L M N A E B C F, G F, G D, H I I L 2 6 2 2 2 4 6 2 4 3 3 3 5 3 8 4 3 8 5 6 6 5 11 4 4 4 5 7 Machines needed ($100/Hour) 3 6 8 0 3 3 2 2 4 2 1 0 4 2 Percent completed after 6 working days 100 100 100 100 100 70 20 95 0 0 0 0 0 0

Step by Step Solution

3.37 Rating (163 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Economics Questions!