Question: Draw the activity on arrow network diagram for the folowing project, Immediately Preceding Activity (IPA) Activity A B A A D B E B,C
Draw the activity on arrow network diagram for the folowing project, Immediately Preceding Activity (IPA) Activity A B A A D B E B,C CRIS Marks) Draw an activity on node network diagram for the project indicated below. Immediately Preceding Activity (IPA) Activity Duration A A 8 6 19 A D B B.C G D,E,F CR(7 Marks) Calculate the Earliest start time for the activities in the 1(b) EV(S Mar ks) Calcukate the latest completion time for the activities in 1(b) EV (5 Marks)
Step by Step Solution
3.53 Rating (156 Votes )
There are 3 Steps involved in it
Ans netuwrk for activityon arrow CA OA D acHvity on node C AON metwork 8 du mn carti... View full answer
Get step-by-step solutions from verified subject matter experts
