Question: Construct the arrow diagram comprising activities A.B..., M.N and O so that the following relationships are fulfilled: 1. A and B (the first activities of

Construct the arrow diagram comprising activities

Construct the arrow diagram comprising activities A.B..., M.N and O so that the following relationships are fulfilled: 1. A and B (the first activities of this project) can start simultaneously. 2. A precedes D.C. 3. B precedes C.E.F. 4. C and E precede G and I. 5.D and G precede H. 6. F.I precede K and L. 7.K.L precede M and N. 8. L precedes H. 9.H.M precede 0. 10. O and N are the terminal activities of the project. D 8 A 103 02/ 104 B E N F K Arrow Diagram