Question: The activities and time estimate (in weeks) for various activities are illustrated below: Activity A ano - - kh B C D E F
The activities and time estimate (in weeks) for various activities are illustrated below: Activity A ano - - kh B C D E F Preceding Activity A B C,B D Optimistic 1 8 2 1 6 4 Time Estimates Most likely 2 10 4 2 8 3 Pessimistic 3 12 6 3 10 8 Draw the network diagram? Determine the critical path Calculate EST, LST, EFT and LFT of the activities on the critical path? Detriment the average estimated duration of the project? What is the probability of finishing the project with in 20 weeks?
Step by Step Solution
3.49 Rating (175 Votes )
There are 3 Steps involved in it
Network diagram for activities and time estimatesin weeks for various activities Name Institution Pr... View full answer