Question: ) Construct the project network presented in the following table. Calculate and report the activities on the critical path and the minimum project duration. Note
) Construct the project network presented in the following table. Calculate and report the activities on the critical path and the minimum project duration. Note calendar days include weekends as days counted.
| Activity | A | B | C | D | E |
| Duration | 6 calendar days | 1 calendar week | 48 contiguous hours | 8 calendar days | 4 calendar days |
| Predecessor | - | A | A | C | B,D |