Question: CONSTRUCTION MANAGEMENT Assignment# 2 Below is a precedence diagram for a small building project. Below each activity is the number of laborers required for that

CONSTRUCTION MANAGEMENT
Assignment#2
Below is a precedence diagram for a small building project. Below each activity is the number of laborers required for that activity. Given a limit of 11 laborers, can the project be completed on time? Use the worksheet below, show your Gantt Chart and labor distribution, show revised labor distribution, show extension of duration, if needed.