Question: Below is a precedence diagram for a small building project. Below each activity is the number of laborers required for that activity. Given a limit

Below is a precedence diagram for a small building project. Below each activity is the number of laborers required for that activity. Given a limit of 10 laborers, can the project be completed on time? Use the worksheet at the end of the page. 20 50 80 ES Node EF UF Float 2 0 10 0 60 90 100 120 6 5 O 7 2 40 70 110 5 Resource Allocation Table (Workdays Priority 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Activity Dur R Rd ES TF
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts