Question: Construction Project Example ( continued ) Consider the construction project defined by the precedence table and the AON network diagram below. table [ [

Construction Project Example (continued)
Consider the construction project defined by the precedence table and the AON network diagram below.
\table[[Activity,Predecessor,\table[[Duration],[(days)]]],[A,--,8],[B,--,10],[C,A,3],[D,A, B,7],[E,A, B,6],[F,C,7],[G,D, F,5],[H,E, G,3]]
1
0 points earned
What is the slack of activity E(in days)?
\table[[,00],[1,],[9,],[3,],[7,]]
0 points earned
How many days can activity G be delayed without delaying the project?
1
5
7
0
 Construction Project Example (continued) Consider the construction project defined by the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!