Question: Construction Project Example ( continued ) Consider the construction project defined by the precedence table and the AON network diagram below. table [ [
Construction Project Example continued
Consider the construction project defined by the precedence table and the AON network diagram below.
tableActivityPredecessor,tableDurationdaysABCADA BEA BFCGD FHE G
points earned
What is the slack of activity in days
table
points earned
How many days can activity be delayed without delaying the project?