Question: Construction Project Example (continued) Consider the construction project defined by the precedence table and the AON 4 1 poins notwork fifiaram helow: What is the

 Construction Project Example (continued) Consider the construction project defined by the

Construction Project Example (continued) Consider the construction project defined by the precedence table and the AON 4 1 poins notwork fifiaram helow: What is the slack of activity E (in days)? 7 0 9 3 1 5 ipoint How many dsys can activity G be delayed without delaying the project? 7 3 5 1 0