Contract #1482 began on April 1, 2012. As of December 31, 2012, the end of the contractors
Question:
Contract #1482 began on April 1, 2012. As of December 31, 2012, the end of the contractor’s accounting year, costs incurred were as follows:
$
Materials issued 480,000
Materials on site, December 31, 2012, 40,000
Labour 720,000
The plant issued to the site on April 1, 2012, 800,000
Written down value of plant December 31, 2012, 560,000
Overheads 120,000
The contract is expected to end in March 2013 and as at December 31, 2012 the cost accountant estimated that the final cost of the contract would be $1,900,000. The full contract price is $1,800,000. Work certified as at December 31, 2012 was valued at $1,400,000. The contractee made progress payments of $1,260,000 up to December 31, 2012.
Required:
- Prepare the Contract Account.
- Prepare the contract P&L account
- Prepare the Contractee Account.
- Calculate the Balance Sheet value of work-in-progress as at December 31, 2012.
- List the items that would be included in the contractor’s Balance Sheet on December 31, 2012.