Question: Control charts for a process have previously been constructed. The X-Bar Chart upper and lower control limits are 92.5 and 88.5, respectively. New samples are
-
Control charts for a process have previously been constructed. The X-Bar Chart upper and lower control limits are 92.5 and 88.5, respectively. New samples are taken from three machines with the following results:
Machine
Measurements
#1
93.4
92.2
91.9
92.7
#2
88.3
95.1
90.6
94.8
#3
92.5
93.1
88.9
90.3
Which machine(s), if any, appear(s) to have an out-of-control process mean based solely on the X-Bar Chart?
Machine #1
Machine #2
Machine #3
Machine #1 and Machine #3
Machine #2 and Machine #3
All of the machines
None of the machines
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts