Question: Corrective action must be taken for a project when a . the actual cost of the activities is less than the funds received for the

Corrective action must be taken for a project when
a. the actual cost of the activities is less than the funds received for the work completed.
b. actual progress to the planned progress shows the progress is ahead of schedule.
c. the actual progress is less than the planned progress.
d. the technical specifications have been met.
 Corrective action must be taken for a project when a. the