Question: Corrective action must be taken for a project when Question 1 0 options: actual progress to the planned progress shows the progress is ahead of

Corrective action must be taken for a project when
Question 10 options:
actual progress to the planned progress shows the progress is ahead of schedule.
the technical specifications have been met.
the actual cost of the activities is less than the funds received for the work completed.
the actual progress is less than the planned progress.