Question: Question 15 Cost Account Planned Value Earned Value Actual Cost 1.2.1 1.3.1 $275 $550 $300 $500 $375 $500 Cost Account Planned Value Earned Value




Question 15 Cost Account Planned Value Earned Value Actual Cost 1.2.1 1.3.1 $275 $550 $300 $500 $375 $500 Cost Account Planned Value Earned Value Actual Cost 1.2.1 1.3.1 $275 $550 $300 $500 $375 $500 Figure 1 Based on the data in Figure 1 above, Cost Account 1.2.1 is ___(of) schedule and cost Figure 1 Based on the data in Figure 1 above, Cost Account 1.3.1 has a schedule variance of variance of $50, $50 $25, $25 $25, $0 $50, $0 -$50, $0 and a cost Figure 1 Based on the data in Figure 1 above, Cost Account 1.2.1 is Ahead, over Behind, under On, under Ahead, on Behind, over (of) schedule and cost
Step by Step Solution
3.31 Rating (160 Votes )
There are 3 Steps involved in it
The detailed answer for the above question is provided below Based on the data ... View full answer
Get step-by-step solutions from verified subject matter experts
