Question: Could you please find the critical path, how many weeks it will take to complete the project, and how much slack activity B has? Thanks

Could you please find the critical path, how many weeks it will take to complete the project, and how much slack activity B has? Thanks so much you're a life saver
Could you please find the critical path, how many
Could you please find the critical path, how many
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) 7 6 2 4 3 ABCDEFG AACBDE B. D E.F 4 6 a. What is the critical path (enter a sequence of letters for critical path, e.g., ABCDFG)? A/ b.How many weeks will it take to complete the project? A c. How much slack does activity B have weeks (enter the values only, e.g. 3)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!