Question: CPM Exercise BIS 420 Task Optimistic Realistic Pessimistic ETD Preceding Task(s) 4 3 3 9 2,3 2 aw 4 .6 8 2 3 5,7 Complete

CPM Exercise BIS 420 Task Optimistic Realistic
CPM Exercise BIS 420 Task Optimistic Realistic Pessimistic ETD Preceding Task(s) 4 3 3 9 2,3 2 aw 4 .6 8 2 3 5,7 Complete the WBS above. Using a network diagram and CPM answer the following (you must show your work to get full credit): 1) what is the earliest finish time for this project: 2) which tasks are on the critical path 3) which tasks have slack, how much slack do they have