Question: CPM Exercise E Task Name Duration (Days) A 5 B 2 C 7 D 8 E 6 END 1. Develop a network diagram based on

CPM Exercise E Task Name Duration (Days) A 5 B 2
CPM Exercise E Task Name Duration (Days) A 5 B 2 C 7 D 8 E 6 END 1. Develop a network diagram based on above data 2. What is the Total Project duration? Predecessors A+2 lag days, B B C,D E