Question: Question 3. (10 pts) By using the Legend given below and information given in the Table, Legend: Early Early Slack Start Finish Activity Name Late

Question 3. (10 pts) By using the Legend given below and information given in the Table, Legend: Early Early Slack Start Finish Activity Name Late Late Start Duration Finish Table: Activity Name Duration (days) Dependence 4 B wo U ODD D 6 E 14 F 5 C G 2 E, F G H 2 3 1 G J 4 HI J 2 a) (3 pts) Construct the Activity on Node (AON) network diagram b) (4 pts) By using the critical path method (CPM), compute the total project duration c) (3 pts) Identify the critical path