Question: CPM Here is the information about the project: Activity Immediate Predecessors activity time A N / A 3 B A 2 C B 1 D

CPM
Here is the information about the project:
Activity Immediate Predecessors activity time
A N/A 3
B A 2
C B 1
D C 1
E G, C 2
F C, D 3
G B 5
H F 4
Answer Q4 to Q7 based on this information. Make sure The Earliest Starting Time for Activity F is 7 before you go on.
Q4. The Earliest Starting Time for Activity E is 6.