Question: Here is the information about the project: Activity Immediate Predecessors Optimistic Time Most Likely Time Pessimistic Time A N/A 2 3 4 B A 1

Here is the information about the project:

Activity Immediate Predecessors Optimistic Time Most Likely Time Pessimistic Time
A N/A 2 3 4
B A 1 2 5
C B 1 2 3
D A 1 2 3
E B 4 5 6
F B, C, D 2 4 6
G F 2 2 6

Answer Q8 to Q10 according to this information. Use 2 decimal points in the calculation. Q8. The mean activity time for activity F is 0.67

True

False

Make sure the Earliest Starting Time of activity F is 7.33. The mean of the Total Project Completion Time is 14 and the standard deviation is around 1.25.

True

False

Which of the following statement is not true?

A.

If we want to be sure (90% sure) that the project will be completed by the day we promised. We should promise 14 days.

B.

The probability that the project will be longer than 12 days is more than 90%.

C.

The 85% confidence interval is between 12.20 and 15.80.

D.

The probability the project will be shorter than 8 days is almost impossible.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!