Question: Here is the information about the project: Activity Immediate Predecessors Optimistic Time Most Likely Time Pessimistic Time A N/A 2 3 4 B A 1
Here is the information about the project:
| Activity | Immediate Predecessors | Optimistic Time | Most Likely Time | Pessimistic Time |
| A | N/A | 2 | 3 | 4 |
| B | A | 1 | 2 | 5 |
| C | B | 1 | 2 | 3 |
| D | A | 1 | 2 | 3 |
| E | B | 4 | 5 | 6 |
| F | B, C, D | 2 | 4 | 6 |
| G | F | 2 | 2 | 6 |
Answer Q8 to Q10 according to this information. Use 2 decimal points in the calculation. Q8. The mean activity time for activity F is 0.67
True
False
Make sure the Earliest Starting Time of activity F is 7.33. The mean of the Total Project Completion Time is 14 and the standard deviation is around 1.25.
True
False
Which of the following statement is not true?
| A. | If we want to be sure (90% sure) that the project will be completed by the day we promised. We should promise 14 days. | |
| B. | The probability that the project will be longer than 12 days is more than 90%. | |
| C. | The 85% confidence interval is between 12.20 and 15.80. | |
| D. | The probability the project will be shorter than 8 days is almost impossible. |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
