Question: Here is the information about the project: Activity Immediate Predecessors Optimistic Time Most Likely Time Pessimistic Time A N / A 2 3 4 B

Here is the information about the project:
Activity Immediate Predecessors Optimistic Time Most Likely Time Pessimistic Time A N/A 234 B A 125 C B 123 D A 123 E B 456 F B, C, D 246 G F 226
Make sure the Earliest Starting Time of activity F is 7.33. The mean of the Total Project Completion Time is14and the standard deviation is around 1.25.