Question: Crash Normal Normal Crash Activity Predecessor Time Time Cost Cost (days) A 3 3 3000 3000 B 5 3 1 3000 9000 9 0 6000

Crash Normal Normal Crash Activity Predecessor

Crash Normal Normal Crash Activity Predecessor Time Time Cost Cost (days) A 3 3 3000 3000 B 5 3 1 3000 9000 9 0 6000 8000 D A,B 6 4 6000 6600 E B 6 6 5000 5000 F C 5 3 7000 9000 G E,F 7 6 2000 4000 IH D 11 8 5000 6500 Given the project crash data above, state the following after crashing the project 5 days: What is the critical path of the project at the end of the crash? What activities are crashed to reduce the project by the 5 days? What is the cost of crashing the project by the 5 days