Question: Crash Normal Normal Crash Activity Predecessor Time Time Cost Cost (days) A 3 3 3000 3000 B 5 3 1 3000 9000 9 0 6000

Crash Normal Normal Crash Activity PredecessorCrash Normal Normal Crash Activity Predecessor

Crash Normal Normal Crash Activity Predecessor Time Time Cost Cost (days) A 3 3 3000 3000 B 5 3 1 3000 9000 9 0 6000 8000 D A,B 6 4 6000 6600 E B 6 6 5000 5000 F C 5 3 7000 9000 G E,F 7 6 2000 4000 IH D 11 8 5000 6500 Given the project crash data above, state the following after crashing the project 5 days: What is the critical path of the project at the end of the crash? What activities are crashed to reduce the project by the 5 days? What is the cost of crashing the project by the 5 days? Draw the 6-cell node flow for this project to complete the questions below: Activity Immediate Activity Time Predecessor (days) A 3 B 7 C A, B 4 D A, B 4 E C 6 F C, D 3 G D 6 H C 8 Questions: 1. State what is the critical path 2. State what is the total completion time of the project: 3. Write out the early and late times for the following activities: A, C, E, H

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!