Question: Crash the project below to its minimum duration using the network given and the information provided. The total normal cost of the project is $

Crash the project below to its minimum duration using the network given and the information provided. The total normal cost of the project is $325. The starting indirect cost of the project is $180, and it drops $20 for every day the project is reduced. Use a new diagram for each day you crash and complete all network information in the diagram each time. Record the information requested in the table provided at the bottom of this assignment for each day crashed and report the optimum project duration.
 Crash the project below to its minimum duration using the network

Step by Step Solution

There are 3 Steps involved in it