Question: Crashing in time management is: Question 1 4 Answer a . The timely input of data to calculate the critical path b . Equivalent to

Crashing in time management is:
Question 14Answer
a.
The timely input of data to calculate the critical path
b.
Equivalent to minimizing float in the project schedule network.
c.
A schedule compression technique that typically includes reducing schedule activity durations and increasing the assignment of resources on schedule activities
d.
A schedule compression technique in which phases or activities that normally would be done in sequence are performed in parallel.
 Crashing in time management is: Question 14Answer a. The timely input