Question: create a forward and bath path analysis of the information below Task Name Duration Cost Predecessors 1 Hanger Permitting 9 days 2 Application 7 days

create a forward and bath path analysis of the information below

Task Name Duration Cost Predecessors
1 Hanger Permitting 9 days
2 Application 7 days 2,800
3 Process time 0 days 0.00 2
4 Order building materials 2 days 560 3
5 Hangar Permitting Complete 0 days 4
6 Hangar Ground Work 65.3 days
7 Survey property 3 days 3,600 5
8 Set elevation 7 days 16,800 7
9 Prepare site for concrete 5 days 12,000 8
10 Construct tarmac and hangar foundation 22 days
11 Build concrete forms 14 days 39,200 9
12 Install plumbing passing through concrete (Internal Sewer) 3 days 1,080 11
13 Schedule code inspections 1 day 360 5, 12
14 Order concrete 1 day 2,800 12
15 Pour concrete 3 days 8,400 12, 14
16 Concrete cured 0 days 0.00 15+7 days
17 Order specialty equipment 2 days
18 Compressors and air systems 1 day 100,440 5
19 Crane and lift equipment 1 day 250,440 5
20 Hangar Groundwork Complete 0 days 0.00 16
21 Hangar Assembly 189.4 days
22 Assemble Frame 30 days 84,000 16, 19
23 Install Crane 7 days 3,460 22
24 Assemble outer structure 30 days 84,000 23
25 Install Hangar Door 14 days 39,200 23
26 Install electrical systems 30 days 8,400 22
27 Install low voltage systems 30 days 9,600 22
28 Install plumbing systems 91.4 days
29 Air systems 30 days 210,800 18, 24
30 Water systems 30 days 260,000 18, 24
31 External Sewer systems 30 days 310,800 24
32 Connect to outside sources 1.4 days 82,763 24, 25, 26, 27, 28, 29, 30, 31
33 Finish inside areas 30 days 342,890 32
34 Hangar Assembly Complete 0 days 0.00 33
35 Open House 1 day 12,500 34

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!